Bathroom Drainage Guide

IWAENG bathroom pods can be planned with either horizontal or vertical drainage. The correct option depends on the original room height, floor structure, drain positions and the building drainage route.

Horizontal drainage

Horizontal drainage uses professional bolt supports beneath the bathroom tray. Allow approximately 120 mm for the service space and 70 mm for the tray thickness and water-retaining upstand, giving a combined installation allowance of 190 mm. The minimum original room height for this installation method is 2650 mm.

Vertical drainage

With vertical drainage, the tray is placed directly on the original floor without bolt supports. The tray thickness is approximately 70 mm, so the finished bathroom floor is raised by 70 mm relative to the original floor. The bathroom pod internal clear height is not calculated by simply subtracting this tray thickness. The minimum original room height for this installation method is 2500 mm.

Floor openings are required at the floor drain and toilet waste outlet. The drain and waste pipes are connected to the main drainage pipework below the floor. Confirm the slab structure, opening permissions, pipe positions and connection access before construction.

Measure the real installation space

Measure the minimum usable length, width and height. Include wall projections, columns, pipes, beams and the lowest ceiling service. If any required minimum dimension is not available, the selected pod configuration cannot be installed.

Use the installation space checker to make a preliminary assessment.